When Resources Are Insufficient, Which Project Should Be Cut —— Not Based on Past Investment or Project Size: Four Criteria for Ranking, Five Project Examples, and Five Ways to Make Things Worse

By: QTank Published: 11/25/2026 Views: 47
Current rating: ★★★☆☆ Rate this Equivalent to 8 ratings

Conclusion First

When resources are insufficient, which project to cut should not be based on how much has already been invested, the project budget, or which boss is pushing it. Instead, it should be based on two factors: how many key resource person-months can truly be released by cutting the project, and the cost required to release these person-months.

Three straightforward criteria:

  1. If the shortfall is less than 15%, do not cut any projects. If the shortfall ratio of key resources (project required person-months minus available person-months, divided by available person-months) is within 15%, it can be absorbed through queuing, scope reduction, and external assistance. Only when the shortfall exceeds 15% and overtime cannot cover it should the decision to cut projects be considered. The reasoning is explained in the table in the first section: when key resource utilization reaches 90%, the average project cycle time is already five times longer than when idle. At this point, keeping an additional project does not mean doing a bit more work; it means prolonging the cycle times of all projects.
  2. The unit for ranking is whether person-months can truly be released, not the value of the project. If a project only occupies 20% of an expert's time, cutting it will not change the other four projects the expert is working on—what is released is a budget item, not capacity.
  3. Sunk costs should not be included in the table, but exit costs must be. Money already invested is only written off in accounting and does not factor into the decision of whether to continue or stop. However, penalties for breach of contract, losses from molds already opened, costs for re-certification, and expenses for team restructuring and knowledge loss are real costs that must be included in the exit cost. Do not overlook the cost of knowledge loss—the replacement cost for a core engineer, based on industry experience, is 50% to 100% of their annual salary.

This article is intended for operations directors, general managers, PMO leaders, and R&D and project leaders. After reading, they should be able to answer a specific question: This quarter, key resources are short by 200 hours. Which projects to cut, how much to cut, and what are the costs?

One, Calculate the Shortfall Before Discussing Cuts

Two steps: identify key resources and calculate the shortfall ratio.

There is only one key resource, or at most two. The criterion is not "which department is the busiest," but rather "which type of person or equipment is essential for all projects." Common examples include an EMC test bench, a mold designer, an engineer who is the only one familiar with a specific communication protocol, or a three-coordinate measuring machine. The method is to list ongoing projects in a matrix based on resource usage and identify the resource that appears most frequently and is irreplaceable. When everything is lacking in the project portfolio, prioritize this column first.

Shortfall ratio = (project required person-months − available person-months) ÷ available person-months. The denominator should only include the actual people and equipment capable of performing the task, not those who theoretically could be trained in three months.

Why use 15% as the threshold? Because this threshold corresponds to the behavior of queuing systems, not arbitrary decisions. Assuming projects arrive randomly and service times vary, the average project cycle time relative to idle time is as follows:

Key Resource Utilization Average Cycle Time ÷ Idle Time Intuitive Meaning (Example: 4-week task)
50% 1.0 times 4 weeks
70% 1.7 times 6.8 weeks
85% 3.3 times 13 weeks
90% 5.0 times 20 weeks
95% 10.0 times 40 weeks

This table explains a recurring phenomenon: the number of projects has not changed, and everyone's effort level remains the same, yet the cycle times of all projects have increased simultaneously. This is not due to a decline in execution but because key resources are being utilized at over 90%. Therefore, "cutting projects" is often not a cost-saving measure but an action to reduce key resource utilization from 95% to below 85%—the money saved is often minimal, but the cycle time saved is significant. For more on how to set the utilization rate and when to reduce it, see What is the Appropriate Utilization Rate for Key Resources.

For this reason, situations with a shortfall of 15% or less should not involve cutting projects. A 15% shortfall is roughly the upper limit that can be absorbed through prioritization, moderate overtime, and scope reduction. Exceeding this limit often results in quality issues and employee turnover within two months. A shortfall exceeding 15% indicates that the total project volume has surpassed the structural capacity of key resources.

Two, Four Criteria for Decision-Making

After entering the decision to cut, follow these four criteria. The first two are scored, while the last two are one-vote veto, not scored.

# Criterion How to Calculate Threshold Action if Passed
1 Resource Releasability R (person-months of key resources occupied by the project ÷ available person-months of the resource for the quarter) R ≥ 30% to cut; 10%~30% to pause; < 10% not to cut Cuts that truly release capacity / Cuts that only save budget / Cuts that are self-harm
2 Remaining ROI K (remaining ETC + exit cost) ÷ (remaining benefit × certainty P) K ≥ 1 to cut; 0.7~1 to reduce scope; < 0.7 to retain Each additional 1 yuan invested does not return 1 yuan
3 Irreversible Gate Whether the project has passed mold manufacturing, certification sample submission, customer PPAP submission, or design freeze Passed gate: exit cost estimated at 40%~70% of incurred expenses; not passed gate: no more than 15% Adjust the numerator of Criterion 2
4 Protection or Veto List One-vote veto, ask each item individually, do not convert to scores See the two lists below Protection = not allowed to cut; Veto = must cut

Criterion 1 is the easiest to skip and the one most likely to result in "cuts with no effect." In most companies' project lists, one engineer is simultaneously involved in five projects, each occupying 20%. Ranking and cutting projects based on their value may save budget on paper, but the engineer's weekly plan remains unchanged—the released time is immediately consumed by firefighting. True releasability depends on the primary responsible person: whether the project's primary responsible person is unique and whether cutting the project allows this person to fully commit to the next project. If you cannot clearly state "what this person will do next week," the decision is ineffective.

For the three numbers in Criterion 2:

  • Remaining ETC: the cost from today to delivery (person-months × internal settlement unit price + external purchases), not the cost already incurred.
  • Exit Cost: penalties for breach of contract, depreciation of molds and long-cycle materials already purchased, costs for re-certification, and expenses for team restructuring and knowledge loss. Do not overlook the cost of knowledge loss—the replacement cost for a core engineer, based on industry experience, is 50% to 100% of their annual salary.
  • Delivery Certainty P: (number of gates passed ÷ total number of gates × historical pass rate for this stage). The historical pass rate should be based on data from similar projects in the company over the past two years; if no data is available, the P value for projects not yet past design freeze should not exceed 0.6.

The same issue of "whether benefits are valid" also appears in project selection for improvement, see Improvement Priority and Project Selection.

The two lists for Criterion 4:

Protection List (not allowed to cut):

  • Breach of contract penalty ≥ remaining project investment
  • Projects that must be completed before the expiration of regulations or certifications (retesting, recertification, customer annual audit)
  • Customer-designated projects or PPAP in progress
  • Platform and shared component projects supporting more than three in-market products
  • Projects that are the sole carriers of unique technical capabilities (cutting them would mean losing the expertise)

Veto List (must cut, regardless of K):

  • Demand source has disappeared: customer cancellation, specification obsolescence, or alternative solutions already in place
  • Two consecutive gate failures without a corrective action plan
  • Project charter's benefit assumptions have been proven false

Why use a one-vote veto system instead of weighted scoring? Because scoring can be averaged out. In a five-dimensional scoring table, a project that is "regulation-mandated" and a project that is "highly valued by leadership" often score 20 points each, leading to mutual cancellation. However, they are fundamentally different types of issues: the former is a constraint, the latter is a preference. Weighted summation results in downgrading constraints to preferences.

Three, Calculation Example

A certain equipment company, in Q1, has 2 structural engineers as key resources, with a total of 960 available hours for the quarter. There are 5 ongoing projects, with a total demand of 1,180 hours, a shortfall of 220 hours, and a shortfall ratio of 22.9%, exceeding 15%, thus entering the decision to cut.

Project Key Resource Usage Remaining Benefit Certainty P Remaining ETC Exit Cost Passed Irreversible Gate K Value
P1 Custom Machine for Client 260 h 1.5 million yuan 0.90 0.6 million yuan 0.55 million yuan Yes (mold opened) 0.85
P2 Platform Standardization 180 h 2.4 million yuan 0.70 0.45 million yuan 0.05 million yuan No 0.30
P3 Internal Pre-Research 120 h — 0.50 0.3 million yuan 0.03 million yuan No Infinite
P4 Client B Modification 320 h 0.9 million yuan 0.85 0.75 million yuan 0.2 million yuan Yes 1.24
P5 Cost Reduction Project 300 h 0.4 million yuan 0.60 0.55 million yuan 0.08 million yuan No 2.63

First, apply the one-vote veto: P2 supports three in-market products, so it is on the protection list and cannot be cut; P1 has contractual penalties, so it is also protected; P3 has no direct benefit and an infinite K value, so it is on the veto list. The remaining projects, P4 and P5, are "candidates for cutting," while P3 is "must be cut."

However, the goal is to "just make up the 220 hours," not to "cut all candidates." Calculate the cost per hour released:

Plan Released Hours Lost Weighted Benefit Exit Cost Total Cost Cost per Hour Released
Cut P3 (120 h) + Reduce P5 scope by 100 h 220 h 0.08 million yuan 0.05 million yuan 0.13 million yuan 591 yuan
Cut P5 entirely 300 h (80 h idle) 0.24 million yuan 0.08 million yuan 0.32 million yuan 1,067 yuan
Cut P4 entirely 320 h (100 h idle) 0.765 million yuan 0.2 million yuan 0.965 million yuan 3,016 yuan

The answer is straightforward: cut P3 and reduce the scope of P5 by one-third, retaining 60% of the delivery content. This releases 220 hours at a cost of 0.13 million yuan. Cutting P5 entirely releases 80 additional hours (which will be idle) at 1.5 times the cost; cutting P4 entirely is seven times more expensive.

There is a common pitfall here that is easy to get wrong: project outputs are not as certain as orders. The contribution margin of an order is fixed at the time of contract signing, while the benefit of a project is always an expected value based on planned delivery. Therefore, when comparing projects, the benefit must be multiplied by the certainty P. Not doing so means treating the most uncertain project as the most valuable—P4's book benefit is 0.9 million yuan, more than double P5's 0.4 million yuan; after multiplying by P, the gap is only 1.6 times, and considering the exit cost (P4 has already opened molds, with an exit cost of 0.2 million yuan), P4 becomes the most expensive. For more on how to prioritize orders when capacity is insufficient, see Which Orders to Prioritize When Capacity is Insufficient.

Four, Five Ways to Make Things Worse

  1. Decide to continue or stop based on "how much has already been invested." The sunk cost trap is easily identifiable: if the meeting includes the phrase "invest another 2 million yuan to break even," and no one asks "how much will be returned from now on by investing another 2 million yuan," the discussion should be redirected to remaining ETC and remaining benefits.
  2. Cut the budget but not the people. Projects are removed from the list, but people remain in place to handle emergencies. Identification method: two weeks after cutting, check the key resource hours ledger. If the expert's weekly plan still includes five projects, it means resources have not been released. This is also the reason for Criterion 1.
  3. Cut projects without closing the project initiation entry. The judgment is simple: if the number of new projects initiated in the quarter exceeds the number of projects completed, and the key resource demand is still above 95% of available hours, it means the cuts were in vain. Three months later, the portfolio will revert to its original state, with additional start-up costs.
  4. Cut 30% across the board. Cutting by a fixed percentage is the easiest and most expensive: it does not distinguish between the protection list, often leading to certification gaps, platform project cuts, and a lack of new products the following year. These losses do not appear in the same year but are reflected in the next year's revenue structure, which is dominated by maintenance orders.
  5. Rank by "which is easier to deliver" and prioritize the easier ones. This appears to improve delivery rates but actually leaves the projects with the lowest marginal benefits. Identification signal: after cutting, the proportion of projects that "can bring in new revenue" in the portfolio decreases, while the proportion of maintenance and modification projects increases.

Five, When Not to Use This Method

  • If the number of projects is less than or equal to the number of key resources. There is no queuing, and the shortfall comes from insufficient manpower. The solution is recruitment, outsourcing, or increasing individual output; cutting projects only pushes the same shortfall to the next quarter.
  • If two consecutive quarters rely on cutting projects to survive. This is already a human resource planning issue. Each cut incurs start-up costs and team morale, and by the third cut, capable people will leave.
  • If projects are strongly coupled. A platform project is a prerequisite for three other projects. Cutting a single project will halt the entire process. In such cases, the solution is to serialize the entire process, not to rank each project individually.
  • During a cash flow crisis. Rank by cash consumption rate and cash inflow, not by discounted benefits. This method assesses "value," while a cash flow crisis asks "whether the company can survive." The two metrics should not be mixed; see How to Compile a Rolling Cash Flow Statement for Three Months.
  • For projects with unverifiable benefits (pre-research, capability building). K is meaningless for them because the denominator is empty. Instead, use a quota system: allocate 10% to 15% of key resources' time to pre-research each quarter, do not rank them, and do not allow reallocation. Including them in the ranking will result in them being cut first every year.

Six, Quarterly Portfolio Review Checklist

Eight items, in order:

  1. Identify the unique key resource (1~2), and write down the reasoning.
  2. Pull the key resource hours ledger (project × person × week), and calculate R for each project.
  3. Calculate the shortfall ratio. If it is within 15%, stop here and do not enter the decision to cut.
  4. Calculate K for each project, and annotate the sources of the remaining ETC, exit cost, and certainty P.
  5. Apply the protection and veto lists, one-vote veto, no scoring.
  6. Rank by "cost per hour released," and stop when the shortfall is met, do not overcut.
  7. Each cut decision must include "what the released person will do next week."
  8. Close the entry: before initiating new projects in the next quarter, ensure the total demand of ongoing projects ≤ key resource available hours × 85%.

The eighth item is the easiest to overlook and the most cost-effective. If you only cut without closing the entry, the portfolio will grow back within three months and incur additional start-up costs. The numbers in this checklist are the same as those reviewed in the monthly business analysis meeting, just with finer granularity. For more on the connection, see What Numbers to Review in the Monthly Business Analysis Meeting.

Knowledge code: 4.4.3 Author: QTank Version: v20261125